A lot has been happening in the country, we are all focused on the drought and trying the best we can to save as many lives as we could. Even when we still have such tragic stories making rounds, it’s sad that the taxpayer risks losing more than Sh400 million
In a report tabled in Parliament on Tuesday, construction of county government office block for Samburu Executives has stalled and the contractor left the site. Ouko said M/s Ole Noor General Hardware Limited was awarded a Sh 285,427,726 contract for the job in 2014.
In Elgeyo Marakwet County, the auditor said completion of the governors’ residence had fallen behind schedule in spite of the county government paying Sh13,873,301.50 to an unnamed company.
“A physical verification of the project on November 2018 revealed that the site remained deserted,” the report read.
In Nandi county, former governor Cleophas Langat entered into a Sh103,383,420 contract with a company on December 2013, to construct the governor’s office but construction works had been abandoned at the time of audit.
Further, the county cannot account for an excess of Sh8 million of irregular payments made to the Council of Governors (CoG), Delta Towers building that houses their liaison offices in Westlands, Nairobi.